In collaboration with the Windmill Hill HOA, the Parks and Recreation Department will install path lighting along the Windmill Hill Greenbelt Trail. Email questions or comments to Shawn.Ray@cedarhilltx.com and check back here for construction updates.
Windmill Hill Greenbelt - Projected Timeline
| Status - Updated 04/27/2023 |
---|
Receive feedback from Community Development Corporation Board | Completed |
Order postcards | Completed |
Mail out to all Windmill Hill residents by 11/25/2022 | Completed |
Receive resident feedback from 11/30/2022 - 01/01/2023
| Completed
|
Week of 01/09/2023 - Begin advertising project for construction | Completed |
Late January 2023 to Early February 2023 - Council consideration | Completed |
June mobilization, material delay may cause postponement | Pending |
August 2023 completion | Pending |